OUR
PROCESS
At Vap Construction, Inc, the post frame building process starts with you. We understand you need a high quality post frame building that suits your needs, so we custom design your building based on your specifications.
STEP
1
The sidewalls are constructed with CCA treated posts on 8′ centers and a 2″x6″ treated bottom plate. The top plate is a double 2″x10″.
STEP
2
The 2″x6″ wallboards are on 24″ spacings. The top is finished using 2″x4″ overlapping purlins. All wallboards and purlins are #2 grade lumber.
STEP
3
Our fastening system incorporates neoprene washer screws. All sidewall posts are supported with V-braces and the gable ends include wind bracing.
STEP
4
Our metal is 29-gauge steel with a 40-year baked enamel coating
STEP
5
Upgraded features at no additional cost include: top and bottom closure strips, eve trim, rat guard, and a steel walk door.
We use only the highest quality materials and a building process that has been tried and tested over the last 25 years. All this is backed by more than 50 years of combined building experience.